Status of Construction / Progress Summary
This report will include construction updates of Kijani Suites Beach Apartments located at Ocean Beach Drive, Malindi- Kenya, as of July 2nd 2024. The report is divided into individual block numbers with full descriptions of the work done. The report also entails the construction update of the showhouse. Also, a photo log of construction activities for the above-mentioned date is provided along with the description of the work done.
Block 1
The interior and exterior painting has been successfully completed, breathing new life into both the indoor and outdoor spaces. Concurrently, the interior block structuring for a three-bedroom unit is underway, laying the foundation for functional and aesthetically pleasing living spaces. The installation of glass windows is now 90% complete, ensuring that natural light and scenic views are seamlessly integrated into the design.
Electrical wiring, fittings, and fixtures are actively being worked on, and door fittings are 90% done. The Galana tiling on the staircases is fully completed, and nearly finished on the verandas. Additionally, the roof terrace and waterproofing efforts are ongoing. With these simultaneous efforts, the project is steadily evolving towards its envisioned state of modernity and functionality.
Block 2
The interior and exterior painting have been successfully completed, giving the space a refreshed and polished appearance. The floor tiling work is nearing completion, adding a durable and aesthetically pleasing foundation to the space. The installation of glass windows in the exterior and staircase areas is 90% done, enhancing both the functionality and the visual appeal of the building. Electrical wiring, fittings, and fixtures are actively being worked on, and door fittings are 90% done. The Galana tiling on the staircases is fully completed, and nearly finished on the verandas. Additionally, the roof terrace and waterproofing efforts are ongoing. With each phase of work advancing steadily, the project is on track to achieve its desired outcome of a modern and inviting environment.
Block 3
The interior and exterior painting have been successfully completed, providing a fresh and vibrant atmosphere to the space. The floor tiling work is fully completed, adding a sleek and durable foundation to the area. The installation of glass windows in the exterior and staircase areas is now 90% complete, enhancing both the aesthetics and functionality of the building. Electrical wiring, fittings, and fixtures are actively being worked on, and door fittings are 90% done. The Galana tiling on the staircases is fully completed, and nearly finished on the verandas. Additionally, the roof terrace and waterproofing efforts are complete.
With all these elements in place, the project has reached a significant milestone, boasting a modern and inviting appearance.
Block 4
The interior and exterior painting have been successfully completed, giving the space a renewed and polished look. The floor tiling work is fully finished, providing a solid and visually appealing foundation. The installation of glass windows in the exterior and staircase areas is 90% complete, adding both charm and functionality to the building. Electrical wiring, fittings, and fixtures are actively being worked on, and door fittings are 90% done. The Galana tiling on the staircases is fully completed, and nearly finished on the verandas.
Additionally, the roof terrace and waterproofing efforts are complete. With each aspect finalized, the project stands as a testament to meticulous attention to detail and craftsmanship, creating a welcoming and refined environment.
Block 5
The interior and exterior painting has been successfully completed, rejuvenating both the indoor and outdoor spaces with fresh coats of paint. The floor tiling work is fully finished, and the installation of glass windows in the exterior and staircase areas is 90% complete, enhancing the aesthetics and functionality of the building. Electrical wiring, fittings, and fixtures are actively being worked on, and door fittings are 90% done.
The Galana tiling on the staircases is fully completed, and nearly finished on the verandas. Additionally, the roof terrace and waterproofing efforts are complete. Plumbing works and wardrobe finishing and fixtures are scheduled to start this week. With these updates, the project is steadily advancing towards its final transformation into a modern and inviting space.
Exterior & Common Areas
The construction of the swimming pool is actively underway, aiming to provide a luxurious recreational facility for residents. The parking lot landscaping and cabro paving are fully completed, ensuring ample and well-structured parking space. Landscaping of recreational spaces, including grass planting and flower gardening, is in progress, focusing on creating a serene and inviting outdoor environment.
SHOWHOUSE
The fittings of windows and doors for the showhouse are complete. The floor tiles of all the rooms have also been fixed. The fixing of wardrobes is also complete. Electrical wiring, fittings, and fixtures are actively being worked on.