Kijani Suites Apartments: Progress Report, April 5th 2024

Status of Construction / Progress Summary

This report will include construction updates of Kijani Suites Beach Apartments located at Ocean Beach Drive, Malindi- Kenya, as of April 5th 2024. The report is divided into individual block numbers with full descriptions of the work done. The report also entails the construction update of the showhouse. Also, a photo log of construction activities for the above-mentioned date is provided along with the description of the work done.

Block 1

The interior and exterior painting has been successfully completed, breathing new life into both the indoor and outdoor spaces. Concurrently, the interior block structuring for a three-bedroom unit is underway, laying the foundation for functional and aesthetically pleasing living spaces. Meanwhile, the installation of glass windows is in progress, ensuring that natural light and scenic views are seamlessly integrated into the design. With these simultaneous efforts, the project is steadily evolving towards its envisioned state of modernity and functionality.

Block 2

The interior and exterior painting have been successfully completed, giving the space a refreshed and polished appearance. Concurrently, the floor tiling work is in progress, adding a durable and aesthetically pleasing foundation to the space. Meanwhile, the installation of glass windows in the exterior and staircase areas is underway, enhancing both the functionality and the visual appeal of the building. With each phase of work advancing steadily, the project is on track to achieve its desired outcome of a modern and inviting environment.

Block 3

The interior and exterior painting have been successfully completed, providing a fresh and vibrant atmosphere to the space. Additionally, the floor tiling work has been finished, adding a sleek and durable foundation to the area. Furthermore, the installation of glass windows in the exterior and staircase areas is now complete, enhancing both the aesthetics and functionality of the building. With all these elements in place, the project has reached a significant milestone, boasting a modern and inviting appearance.

Block 4

The interior and exterior painting have been successfully completed, giving the space a renewed and polished look. Furthermore, the floor tiling work has been finished, providing a solid and visually appealing foundation. Additionally, the installation of glass windows in the exterior and staircase areas is now complete, adding both charm and functionality to the building. With each aspect finalized, the project stands as a testament to meticulous attention to detail and craftsmanship, creating a welcoming and refined environment.

Block 5

The interior and exterior painting has been successfully completed, rejuvenating both the indoor and outdoor spaces with fresh coats of paint. Furthermore, the installation of glass windows in the exterior and staircase areas is now finished, enhancing the aesthetics and functionality of the building. Meanwhile, the installation of washroom tiles is currently in progress, ensuring that every aspect of the project is meticulously attended to. With these updates, the project is steadily advancing towards its final transformation into a modern and inviting space.

SHOWHOUSE

Fittings of windows and doors for the showhouse are complete. The floor tiles of all the rooms have also been fixed. Fixing of wardrobes is also complete.