Status of Construction / Progress Summary
This report will include construction updates of Kijani Suites Beach Apartments located at Ocean Beach Drive, Malindi- Kenya, as of August 1st 2024. The report is divided into individual block numbers with full descriptions of the work done. The report also entails the construction update of the showhouse. Also, a photo log of construction activities for the above-mentioned date is provided along with the description of the work done.
Block 1
The interior and exterior painting has been successfully completed, breathing new life into both the indoor and outdoor spaces.Electrical wiring, fittings, and fixtures are actively being worked on, and door fittings are 90% done.
Block 2
Interior and exterior painting is complete. Floor tiling work ongoing. Electrical wiring, fittings, and fixtures are actively being worked on, and door fittings are almost done. The Galana tiling on the staircases is fully completed, and nearly finished on the verandas.
Block 3
Interior and exterior painting is complete. Floor tiling work complete. Exterior and staircase area glass windows installation complete. Electrical wiring, fittings, and fixtures are actively being worked on, and door fittings is almost done .
Block 4
Interior and exterior painting is complete. Floor tiling work complete. Exterior and staircase area glass windows installation complete. Additionally, the roof terrace and waterproofing efforts are complete. Electrical wiring, fittings, and fixtures are actively being worked on, and door fittings is almost done .
Block 5
The interior and exterior painting has been successfully completed, rejuvenating both the indoor and outdoor spaces with fresh coats of paint. Furthermore, the installation of glass windows in the exterior and staircase areas is now finished, enhancing the aesthetics and functionality of the building. Meanwhile, the installation of washroom tiles is currently in progress, ensuring that every aspect of the project is meticulously attended to. With these updates, the project is steadily advancing towards its final transformation into a modern and inviting space.
SHOWHOUSE
Fittings of windows and doors for the showhouse are complete. The floor tiles of all the rooms have also been fixed. Fixing of wardrobes is also complete.
Exterior & Common Areas
The construction of the swimming pool is actively underway, with laying of the slab successfully done. The parking lot landscaping and cabro paving are fully completed and cleared. Landscaping of recreational spaces, including grass planting and flower gardening, is in progress, focusing on creating a serene and inviting outdoor environment. Bio-digesters have also been installed successfully.