This report will include construction updates of Kijani Suites Beach Apartments located at Ocean Beach Drive, Malindi- Kenya, as of April 30th, 2023. The report is divided into individual block numbers with full descriptions of the work done. The report also entails the construction update of the showhouse. Also, a photo log of construction activities for the above-mentioned date is provided along with the description of the work done.
Block 1
Construction of the ground floor, first floor, and second floor is complete. The formwork and structural steel are currently being laid for the casting of the rooftop, while block work for all the floors has been completed.
Block 2
The block work for all floors has been finished, and the casting of the rooftop is also complete. At present, hacking for plumbing and electricity is underway.
Block 3
Construction for the ground floor, first floor, second floor, and third floor is now complete. Piping for electricity and plumbing is currently in progress, while internal plastering has already commenced.
Block 4
The construction of the ground floor, first floor, second floor, and third floor is complete. Laying of the top slab is also complete. Internal plastering is underway. Pipping for water and electricity is almost complete.
Block 5
The construction of the ground floor, first floor, second floor, and third floor is complete. The construction of the slab is also complete. Painting of the interior walls is ongoing. Plastering of the exterior walls is ongoing
SHOWHOUSE
Fittings of windows and doors for the showhouse are complete. The floor tiles of all the rooms have also been fixed. Fixing of wardrobes is also complete.