Kijani Suites Apartments: Progress Report, Jan 5th 2024

Status of Construction / Progress Summary

This report will include construction updates of Kijani Suites Beach Apartments located at Ocean Beach Drive, Malindi- Kenya, as of January 5th 2024. The report is divided into individual block numbers with full descriptions of the work done. The report also entails the construction update of the showhouse. Also, a photo log of construction activities for the above-mentioned date is provided along with the description of the work done.

Block 1

Preparation for interior and exterior painting is ongoing. Fabrication for aluminium windows and doors is ongoing, awaiting fixing

Block 2

Interior and exterior surfaces have been fully painted. Fixing of door frames is in progress, and fabrication of aluminium windows and doors is in progress for installation.

Block 3

Interior and exterior surfaces have been fully painted. Fixing of door frames is in progress, and fabrication of aluminium windows and doors is in progress for installation.

Block 4

The painting for both interior and exterior surfaces is in progress. Currently, aluminium windows and doors are being fabricated for installation, and work on fixing door frames is in progress.

Block 5

The painting for both interior and exterior surfaces has been finished. The installation of aluminum windows and doors is 75% complete. Interior door frames have been fitted, and the tiling of the floor area is also complete.

SHOWHOUSE

Fittings of windows and doors for the showhouse are complete. The floor tiles of all the rooms have also been fixed. Fixing of wardrobes is also complete.