Kijani Suites Apartments: Progress Report, Oct-Nov 2023

Status of Construction / Progress Summary

This report will include construction updates of Kijani Suites Beach Apartments located at Ocean Beach Drive, Malindi- Kenya, as of Oct-Nov 2023. The report is divided into individual block numbers with full descriptions of the work done. The report also entails the construction update of the showhouse. Also, a photo log of construction activities for the above-mentioned date is provided along with the description of the work done.

Block 1

Interior and exterior plastering are almost complete, setting up for painting.

Block 2

Exterior plastering complete. Interior plastering is also almost complete. Floor screening is ongoing and staircase interior plastering is in full swing.

Block 3

Interior and exterior plastering are complete. Floor screening is also complete. Staircase interior plastering ongoing.

Block 4

Exterior plastering is complete. Piping for water and electricity is complete. First coat for the interior paiting is done, awaiting the final painting works.

Block 5

1st and 2nd paint coats are done on the exterior and interior surfaces. Aluminum glazing for windows and doors is now in progress. Installtion of mazeras in ongoing on the staircase

SHOWHOUSE

Fittings of windows and doors for the showhouse are complete. The floor tiles of all the rooms have also been fixed. Fixing of wardrobes is also complete.