Status of Construction / Progress Summary
This report will include construction updates of Kijani Suites Beach Apartments located at Ocean Beach Drive, Malindi- Kenya, as of September 25th, 2023. The report is divided into individual block numbers with full descriptions of the work done. The report also entails the construction update of the showhouse. Also, a photo log of construction activities for the above-mentioned date is provided along with the description of the work done.
Block 1
Internal plastering is almost complete in preparation for exterior plastering.Installation of vent blocks is complete.
Block 2
Interior plastering & hacking for plumbing and electricity are complete awaiting exterior plastering. Installation of vent blocks is complete.
Block 3
Piping for electricity and plumbing is complete. Interior and exterior plastering are complete. Installation of vent blocks is complete awaiting exterior painting.
Block 4
Exterior plastering is complete. Piping for water and electricity is complete. Installation of vent blocks is also complete. Interior painting is complete awaiting exterior painting.
Block 5
Painting of the interior walls is complete. Plastering of the exterior walls is complete. Installation of vent blocks is also complete. Exterior painting is almost complete
SHOWHOUSE
Fittings of windows and doors for the showhouse are complete. The floor tiles of all the rooms have also been fixed. Fixing of wardrobes is also complete.